Public sector solar projects in Ireland

9 solar installations at Irish hospitals, colleges, councils and water plants are listed here with size, installer and source. The largest is Causeway Hospital, Coleraine at 1.2 MW. The planning register holds a further 79 applications.

Prices last reviewed October 2026

Which hospitals, colleges, councils and water plants have installed solar?

SiteCountySizeInstallerSource
Causeway Hospital, Coleraine2025Londonderry (NI)1.2 MWNot namedNorthern Health and Social Care Trust
University of Galway campusGalway500 kWNot namedUniversity of Galway
Defence Forces, Casement Aerodrome Hangar 5Dublin358 kWPinergy SolarElectricPinergy
Wicklow County Council, County Buildings2022Wicklow300 kWEnerpowerWicklow County Council
HSE St Mary's campus, Phoenix Park2023Dublin100 kWNot namedSEAI
Mayo County Council, Áras an ChontaeMayo84 kWNot namedMayo County Council
UCC, ORB building extension2020Cork42 kWNot namedUniversity College Cork
Marine Institute HQ, Oranmore2024Galway783 panelsActiv8Marine Institute
Uisce Éireann, Thurles treatment plant2020Tipperary230 panelsGlan Agua MEICUisce Éireann

Why does solar suit hospitals, colleges, councils and water plants?

Public bodies have to cut emissions by 2030. Water and wastewater plants pump all day and have fenced land for ground arrays.

  • Causeway Hospital, Coleraine: Largest PV system on any NI health building; 119.45 tonnes of CO2 saved in its first year; installer not named.
  • University of Galway campus: Snippet-only: 500 kW installed across campus rooftops with a further 500 kW scoped; installer not stated.
  • Defence Forces, Casement Aerodrome Hangar 5: On a west-facing hangar roof; the largest installation in the Defence Forces estate.
  • Wicklow County Council, County Buildings: Snippet-only: solar carport over 107 parking spaces, about 1,600 sq m, producing since summer 2022.
  • HSE St Mary's campus, Phoenix Park: Snippet-only: installed over three months in 2023, with 50 kW of it on the 100-bed hospital unit; installer not stated.

What costs and savings have been published?

These are the figures the business or its installer gave. They have not been audited.

  • Causeway Hospital, Coleraine1.2 MW
    Cost
    £1.2 million
    Saving
    about £141.7k in the first year

    Source: Northern Health and Social Care Trust

  • Wicklow County Council, County Buildings300 kW
    Share of use
    sized to 40% of building load
    Output
    265,800 to 285,000 kWh a year

    Source: Wicklow County Council

  • Uisce Éireann, Thurles treatment plant
    Share of use
    10% cut in imports
    Output
    83,264 kWh a year

    Source: Uisce Éireann

What is in the planning register?

The register has 79 applications for solar at this kind of premises, and 66 were granted. The named sites are below, largest first. "Granted" is permission to build. A scheme is shown as built only where a published report says so.

SiteCountySize applied forStatusPlanning record
Ballymore Eustace Water Treatment PlantKildare880 kWGranted2022, ref 221371
Cavanhill Water Treatment PlantLouth840 kWGranted2024, ref 2460066
KCETBKilkenny600 kWGranted2026, ref 2660382
Dunshaughlin Water Treatment PlantMeath415 kWGranted2024, ref 2460084
Osberstown Wastewater Treatment PlantKildare325 kWGranted2022, ref 221343
Ballyboden Water Treatment PlantDublin260 kWGranted2024, ref SD24A/0069W
West Pier Pumping StationDublin235 kWGranted2024, ref D24A/0140
Castletown Tara Wastewater Treatment PlantMeath200 kWGranted2022, ref 221449
St. Mary's Abbey, GlencairnWaterford150 kWGranted2026, ref 2660135
Ballany Water Treatment PlantWestmeath145 kWGranted2023, ref 2347
Show 15 more applications
SiteCountySize applied forStatusPlanning record
Athlone Wastewater Treatment PlantWestmeath130 kWGranted2022, ref 227
MTU North CampusKerry125 kWUnder construction2026, ref 267
Navan Wastewater Treatment FacilityMeath110 kWGranted2022, ref 22576
The Office of Public Works, TrimMeath105 kWBuilt2020, ref TA200883
Moate Wastewater Treatment PlantWestmeath105 kWGranted2023, ref 2360423
Trim Wastewater Treatment PlantMeath100 kWGranted2023, ref 23417
Castlepollard Wastewater Treatment PlantWestmeath100 kWGranted2022, ref 22496
St. Anthony's Nursing HomeLimerick94 kWWithdrawn2022, ref 22458
Athy Wastewater Treatment PlantKildare70 kWGranted2022, ref 22173
Ballivor Wastewater Treatment PlantMeath55 kWGranted2023, ref 2360107
St. Joseph's HospitalDonegal52 kWGranted2024, ref 2461387
Ferbane Wastewater Treatment WorksOffaly45 kWGranted2021, ref 21486
Glendalough Hermitage CentreWicklow37 kWGranted2024, ref 2460730
Nenagh Sewage Treatment PlantTipperary35 kWBuilt2017, ref 17601274
Confey CollegeKildare30 kWBuilt2017, ref 17132

Where to go next

Common questions

Pricing a system for your business?

Get commercial solar quotes

Tell us about the building and an installer will price a system for it.

Step 1 of 3

Where are you at?