Manufacturing solar projects in Ireland

19 solar installations at Irish factories are listed here with size, installer and source. The largest is Mannok, Cavan at 6 MW. The planning register holds a further 52 applications.

Prices last reviewed October 2026

Which factories have installed solar?

SiteCountySizeInstallerSource
Mannok, Cavan2026, under constructionCavan6 MWActiv8 Solar EnergiesEngineers Ireland
Bombardier wing plant, Belfast2014Antrim (NI)3.6 MWSALIIS RenewablesDowning
Carey Glass, Nenagh2023Tipperary2.7 MWESB Smart Energy ServicesESB
Gyproc (Saint-Gobain), Kingscourt2026Cavan2.5 MWActiv8ThinkBusiness
Kingspan Environmental, Portadown2016Armagh (NI)1.3 MWKingspan EnergySpecification Online
Irish Cement, Platin Works2026Meath1 MWNot namedGlobal Cement
AMS (Architectural & Metal Systems), Little Island2023Cork993 kWPV GenerationPV Generation
Kyte Powertech, CavanCavan950 kWUrbanVoltUrbanVolt
Tricel, Killarney2021Kerry750 kWEnerpowerTricel
McGowans Print350 kWUrbanVoltUrbanVolt
Techcrete, BalbrigganDublin320 kWAlternative Energy Ireland (AEI)Alternative Energy Ireland
Kingspan Insulation, Castleblayney2016Monaghan300 kWKingspan ESB joint ventureESB
Show 7 more projects
SiteCountySizeInstallerSource
IJM Timber250 kWUrbanVoltUrbanVolt
Northstone Materials, Toome2024Antrim (NI)232 kWNot namedRoofing Today
Ire Wel Pallets, GoreyWexford195 kWEnerpowerEnerpower
Wexford Viking GlassWexford180 kWUrbanVoltUrbanVolt
Cedarwood Furniture180 kWUrbanVoltUrbanVolt
Folens70 kWUrbanVoltUrbanVolt
Burgmann Packings66 kWUrbanVoltUrbanVolt

Why does solar suit factories?

Large, low-pitched factory roofs take several hundred kWp without using any ground, and daytime shifts match daytime output.

  • Mannok, Cavan: Covers 3.88 ha of factory roofs and will be the largest rooftop installation in Ireland; panels given as 9,678 or about 10,000.
  • Bombardier wing plant, Belfast: Snippet-only: 14,000 panels on 600,000 sq ft of roof, managed by Downing with operation and maintenance by Anesco.
  • Carey Glass, Nenagh: Completion was set for summer 2023; local press later called it the largest roof-mounted installation in the country.
  • Gyproc (Saint-Gobain), Kingscourt: Concrete-ballasted array because no ground penetration was allowed; one report says the site is a former landfill.
  • Kingspan Environmental, Portadown: Snippet-only: built in about 12 weeks on a new 18,000 sq m insulated-panel roof; billed in 2016 as the largest rooftop array on the island.

What costs and savings have been published?

These are the figures the business or its installer gave. They have not been audited.

  • Bombardier wing plant, Belfast3.6 MW
    Cost
    around £3.5 million
    Share of use
    around a quarter
    Output
    about 3,000 MWh a year

    Source: Downing

  • Carey Glass, Nenagh2.7 MW
    Share of use
    up to 13%
    Output
    about 2.4 GWh a year

    Source: ESB

  • Gyproc (Saint-Gobain), Kingscourt2.5 MW
    Saving
    about €230,000 a year
    Share of use
    up to 15%
    Output
    about 2,235 MWh a year

    Source: ThinkBusiness

  • Kingspan Environmental, Portadown1.3 MW
    Share of use
    30% of daytime demand
    Output
    1.1 to 1.3 GWh a year

    Source: Specification Online

  • AMS (Architectural & Metal Systems), Little Island993 kW
    Saving
    €200,000+ (project page); €300,000 (commercial page)
    Output
    about 862.6 MWh a year
    Payback
    about 5 years

    Source: PV Generation

  • Kyte Powertech, Cavan950 kW
    Share of use
    20%

    Source: UrbanVolt

Show 8 more projects
  • Tricel, Killarney750 kW
    Share of use
    25%
    Output
    776,000 kWh (PV Europe); Tricel cites 561,000 kWh displaced

    Source: Tricel

  • McGowans Print350 kW
    Share of use
    25%

    Source: UrbanVolt

  • Techcrete, Balbriggan320 kW
    Saving
    €45,000 a year
    Payback
    5.5 years

    Source: Alternative Energy Ireland

  • IJM Timber250 kW
    Share of use
    26%

    Source: UrbanVolt

  • Wexford Viking Glass180 kW
    Share of use
    22%

    Source: UrbanVolt

  • Cedarwood Furniture180 kW
    Share of use
    35%

    Source: UrbanVolt

  • Folens70 kW
    Share of use
    44%

    Source: UrbanVolt

  • Burgmann Packings66 kW
    Share of use
    53%

    Source: UrbanVolt

What is in the planning register?

The register has 52 applications for solar at this kind of premises, and 43 were granted. The named sites are below, largest first. "Granted" is permission to build. A scheme is shown as built only where a published report says so.

SiteCountySize applied forStatusPlanning record
Irish Cement Limerick WorksLimerick2.5 MWAwaiting decision2026, ref 2660857
EI ElectronicsClare565 kWBuilt2022, ref 22773
EI ElectronicsClare505 kWAwaiting decision2026, ref 2660536
Oldleighlin QuarryCarlow428 kWGranted2022, ref 22238
Ballyhandle QuarryCork420 kWGranted2026, ref 26/0801
FAAC ElectronicsDublin307 kWWithdrawn2026, ref RED26A/0019W
Kellymount QuarryKilkenny258 kWGranted2022, ref 22399
Avoncourt PackagingCork216 kWGranted2022, ref 2241608
Avoncourt PackagingCork199 kWGranted2021, ref 2139886
Holdensrath QuarryKilkenny196 kWGranted2022, ref 22400
Show 11 more applications
SiteCountySize applied forStatusPlanning record
Euro Quality CladdingKildare119 kWAwaiting decision2026, ref 2660598
Mid Cork Pallets and PackagingMeath82 kWGranted2021, ref 211054
A.W. EnnisCavan3,964 m²Built2020, ref 2049
Pat O'Donnell & CompanyDublin992 panelsGranted2022, ref 5149/22
Sika HouseDublin594 m²Granted2025, ref WEB5733/25
Tillotson IrelandKerry577 m²Granted2025, ref 25123
J Grenan & SonsOffaly2,476 m²Granted2021, ref 21536
Grant EngineeringOffaly3,602 m²Granted2024, ref 2490
Birr Enterprise CentreOffaly1,340 m²Awaiting decision2025, ref 25127
Birr Enterprise CentreOffaly1,339 m²Granted2026, ref 2616
EattoDublin279 panelsGranted2022, ref SD22A/0106

Where to go next

Common questions

Pricing a system for your business?

Get commercial solar quotes

Tell us about the building and an installer will price a system for it.

Step 1 of 3

Where are you at?